STAGE 1 – 19 APRIL 2009 (SUNDAY)
|
Start Timetable Location : Kuala Selangor Bus Station Jalan Melati 3/2 Start Time : 1000hrs
|
Finish Timetable Location : Old Ipoh Town Hall, Jalan Panglima Bukit Gantang Wahab Estimated Finish Time : 1400hrs (Fast Schedule)
|
|
TIME
|
ACTIVITIES
|
|
0600
|
Road closure at start area
|
|
1245
|
Road reopens
|
|
|
TIME
|
ACTIVITIES
|
|
0700
|
Road closure at Finish Area
|
|
1730
|
Roads reopen
|
|
Route:
Kuala Selangor Bus Station, Jalan Melati 3/2, Kuala Selangor (Start) >> Tg. Karang >> Sekinchan >> Sg. Besar >> Sabak Bernam >> Jendarata >> Teluk Intan >> Mambang Diawan >> Kampar >> Gopeng >> Old Ipoh Town Hall, Jalan Panglima Bukit Gantang Wahab, Ipoh (Finish).
|
STAGE 2 – 20 APRIL 2009 (MONDAY)
Start Timetable Location : Dewan Bandaraya Ipoh, Persiaran Bandaraya Start Time : 1100hrs
|
Finish Timetable Location : Dataran Jam Besar Sungai Petani / Jalan Ibrahim Estimated Finish Time : 1530hrs (Fast Schedule)
|
|
TIME
|
ACTIVITIES
|
|
0600
|
Road closure at start area
|
|
1345
|
Road reopens
|
|
|
TIME
|
ACTIVITIES
|
|
0800
|
Road closure at Finish Area
|
|
1900
|
Roads reopen
|
|
Route:
Dewan Bandaraya Ipoh, Persiaran Bandaraya, Ipoh (Start) >> Chemor >> Sg. Siput >> Kuala Kangsar >> Padang Rengas >> Changkat Jering >> Masjid Tinggi >> Parit Buntar >> Nibong Tebal >> Kulim >> Tasik Gelugor >> Pinang Tunggal >> Pinang Tunggal >> Dataran Jam Besar Sungai Petani / Jalan Ibrahim, Sungai Petani (Finish).
STAGE 3 – 21 APRIL 2009 (TUESDAY)
|
Start Timetable Location : Arked Perniagaan Gerik / Jalan Sultan Iskandar (FT76) Start Time : 1100hrs
|
Finish Timetable Location : Medan Selera Payung,Tanah Merah/ Jalan Pasir Mas-Tanah Merah (FT129) Estimated Finish Time : 1530hrs (Fast Schedule)
|
|
TIME
|
ACTIVITIES
|
|
0730
|
Road closure at start area
|
|
1345
|
Road reopens
|
|
|
TIME
|
ACTIVITIES
|
|
0745
|
Road closure at Finish Area
|
|
1900
|
Roads reopen
|
|
Route:
Arked Perniagaan Gerik, Jalan Sultan Iskandar, Gerik (FT76) (Start) >> Tasik Temenggor >> Titiwangsa >> Jeli >> Bukit Bunga >> Medan Selera Payung, Tanah Merah / Jalan Pasir Mas-Tanah Merah (FT129) (Finish).
STAGE 4 – 22 APRIL 2009 (WEDNESDAY)
|
Start Timetable Location : Pejabat Tanah Pasir Mas, Jalan Pasir Mas-Kota Bharu (FT3) Start Time : 1100hrs
|
Finish Timetable Location : Dataran Syahbandar / Jalan Sultan Zainal Abidin Estimated Finish Time : 1500hrs (Fast Schedule)
|
|
TIME
|
ACTIVITIES
|
|
0730
|
Road closure at start area
|
|
1345
|
Road reopens
|
|
|
TIME
|
ACTIVITIES
|
|
0730
|
Road closure at Finish Area
|
|
1900
|
Roads reopen
|
|
Route:
Pejabat Tanah Pasir Mas, Jalan Pasir Mas-Kota Bharu (FT3)(Start) >> Kubang Kerian >> Peringat >> Kg. Tok Bali >> Kuala Besut >> Kg. Tembila >> Merang >> Wakaf Tengah >> Pulau Duyong >> Dataran Syahbandar, Jalan Sultan Zainal Abidin, Kuala Terengganu (Finish).
STAGE 5 – 23 APRIL 2009 (THURSDAY)
|
Start Timetable Location : Dataran Syahbandar / Jalan Sultan Zainal Abidin Start Time : 1000hrs
|
Finish Timetable Location : Padang Perbandaran Kuantan / Jalan Mahkota Estimated Finish Time : 1430hrs (Fast Schedule)
|
|
TIME
|
ACTIVITIES
|
|
0630
|
Road closure at start area
|
|
1245
|
Road reopens
|
|
|
TIME
|
ACTIVITIES
|
|
0715
|
Road closure at Finish Area
|
|
1800
|
Roads reopen
|
|
Route:
Dataran Syahbandar, Jalan Sultan Zainal Abidin, Kuala Terengganu (Start) >> Marang >> Merchang >> Rantau Abang >> Dungun >> Paka >> Kertih >> Chukai >> Cherating >> Beserah >> Padang Perbandaran Kuantan, Jalan Mahkota, Kuantan (Finish).
STAGE 6 – 24 APRIL 2009 (FRIDAY)
|
Start Timetable Location : Taman Jaya Gading / Lorong Jaya Gading 13 Start Time : 0830hrs
|
Finish Timetable Location : Bandar Bera / Jalan Besar (FT10) Estimated Finish Time : 1145hrs (Fast Schedule)
|
|
TIME
|
ACTIVITIES
|
|
0500
|
Road closure at start area
|
|
1115
|
Road reopens
|
|
|
TIME
|
ACTIVITIES
|
|
0630
|
Road closure at Finish Area
|
|
1515
|
Roads reopen
|
|
Route:
Taman Jaya Gading, Lorong Jaya Gading 13, Kuantan (Start) >> Gambang >> Paya Bungor >> Seri Jaya >> Maran >> Temerloh >> Mengkarak >> Bandar Bera, Jalan Besar, Bera (FT10) (Finish).
STAGE 7 – 25 APRIL 2009 (SATURDAY)
|
Start Timetable Location : Universiti Perguruan Sultan Idris Start Time : 1000hrs
|
Finish Timetable Location : Hotel Seri Malaysia Gohtong Jaya / Jalan Jati Estimated Finish Time : 1315hrs (Fast Schedule)
|
|
TIME
|
ACTIVITIES
|
|
0600
|
Road closure at start area
|
|
1245
|
Road reopens
|
|
|
TIME
|
ACTIVITIES
|
|
0730
|
Road closure at Finish Area
|
|
1645
|
Roads reopen
|
|
Route:
Universiti Perguruan Sultan Idris, Jalan Ketoyong, Tanjung Malim (Start) >> Kalumpang >> Kerling >> Kuala Kubu Bharu >> Rawang >> Bukit Lagong >> Batu Caves >> Tasik Batu >> Ulu Yam Baru >> Hotel Seri Malaysia Gohtong Jaya, Jalan Jati, Genting Highlands (Finish).
STAGE 8 – 26 APRIL 2009 (SUNDAY)
|
Start Timetable Location : Dataran Merdeka, Kuala Lumpur Start Time : 1500hrs Estimated Finish Time : 1630hrs
|
|
|
TIME
|
ACTIVITIES
|
|
0900
|
Road closure at Start / Finish
|
|
1930
|
Road reopens
|
|
|
Route:
Dataran Merdeka, Kuala Lumpur (Start) >> Leboh Pasar Besar >> Leboh Ampang >> Jalan Tun Perak >> Jalan Raja Chulan >> Jalan Sultan Ismail >> Jalan P. Ramlee >> Jalan Ampang >> Jalan Sultan Ismail >> Jalan Tuanku Abdul Rahman >> Dataran Merdeka, Kuala Lumpur (Finish).